Tentative Timeline
Project Phase |
Timelines |
Phase 1 (yellow on the map): Classroom Addition in the 4th and 5th Grade Wing |
January 2024 - June 2024 |
Phase 2 (front lawn): Storm Retention System |
February 2024 - May 2024 |
Phase 3 (green on the map): PreK Classrooms Renovation |
June 2024 - August 2024 |
Phase 4 (red on the map): Hawk Hall Addition |
July 2024 - January 2025 |